Project Meeting 2020.10.08
Ben Stabler edited this page Oct 8, 2020
·
17 revisions
5b/6a Task 1 Project Management (5b milestone)
6a Task 1 Project Management (6a milestone)
- Technical calls going well, any feedback?
- Let's discuss getting started on the 6a scope
- SEMCOG coordination plan and inviting Jeff Newman to our developer call
5b Task 2 Strategic Planning (milestone)
- Any comments on the updated version of the plan
- I still need to add the optional test system paragraph and development roadmap
5b Task 10 Support for Three Zone Systems and TVPB (milestone)
- Jeff finished adaptive chunking, which will speed up existing models and help with TVPB memory management
- Jeff now setting up the marin tm2 work tour mode choice example
- After that, work on caching / parallelization
- Should we do some more performance tuning (such as better manage data types) since Jeff is into that part of the code now? Since TVPB leads to some memory issues, should we maybe revise our approach? Let's discuss on Tuesday.