Overview

This is a list of the remaining work and items that may be needed

General

RCBOs of appropriate type and ratings are needed before we can make the system fully safe.

List of circuits:

DB1 (arts) - TPN

List of circuits and requirements:

  • 20A Type C RCBO for metalworking
  • 20A Type C RCBO for welding
  • 20A Type C RCBO for dado rails/etc
  • 20A Type C RCBO for green room
  • 20A Type C MCB for water heater
  • 20A Type C RCBO for classroom sockets
  • 63A Type C MCB TPN: sub main DB2

20A single pole RCBO (6kA) £26.63 each 5 20A single pole MCB (10kA) £8.56 each 1

total: £141.71

We now have 5 C RCBOs ready for fitting

Note, this is a memshield 2 board, standard eaton rcbos will not fit into this board.

DB2 - TPN

This is a Crabtree Polestar board

  • 10A Type C RCBO for lights #1
  • 10A Type C RCBO for lights #2
  • 20A Type C RCBO for main radial 1
  • 20A Type C RCBO for main radial 2
  • 20A Type C RCBO for electronics area
  • 20A Type C RCBO for kitchen area
  • 20A Type C MCB for kitchen water heater
  • 20A Type C MCB for under kitchen sockets
  • 20A Type C RCBO for cnc room

[ note, there's a one breaker with two circuits ]

  • entrance circuit is coupled with electronics i think

10A RCBO (6kA) type C 30mA £25.33 each 2 20A RCBO (6kA) type C 30mA £25.33 each 5 20A MCB (10kA) type C £5.56 each 2

We have 3 20A C RCBOs for fitting We have 2 10A C RCBOs for fitting There are 5 more C RCBOs on order [19th Nov 2019]

total: £188.43

Worst case for all boards is: £330.14

Emergency lighting

This requires a full test to ensure that the lights run for the required time and that there are sufficient lights for anyone to make an emergency exit.

Note, the main area may require some more emergency lighting.

The landlord's supply currently runs the lighting on the outside edge of the hackspace. We may want to leave this for the moment as it is all permanently on.

Main lighting

Power draw checks need to be made and then any further action can be taken. It is possible some of the old flourescent tube fittings will need to be replaced.

It has been noted fititng LED tubes and switches has significantly reduced the electricity bill. Changing all tubes out should be considered or replacing the tubes entirely in the areas where more light is required.

Changing out the two flourescent tubes in snackspace for LED ones has reduced the power draw on the circuit from 1.5A to 0.2A (measured by current-clamp meter) which shows significant improvement. Note, one of the tubes was already dying and needed to be replaced due to repeated failures to start.

Main toilet

The emergency alarm has been fitted and needs final test. It is possible an second sounder in the main area will be added before completion.

There are 1 or 2 32W LED panels the same as the back of the stage to be fitted to provide lighting. The LED panels have been purchased.

If extraction is required a switched/fuse will need to be fitted and appropriate fan isolation. This should not require extra expense apart from the purchase of a suitable extraction fan.

Water heater

There is a 2.5kW water heater which is intended to provide hot water to the classroom area, the main toilet and possibly also the green room sink.

This will need a separate supply and fused connection unit. We should have the connection parts, but will need enough cable.

The location for this will need to be determined, but it could be put in the area above the green room as it is close to water and electrical feed.

Notes, do we need to put copper pipe on the in/out and earth bond this to the main earth feed?

Adam D. Horden - earthing to be discussed after initial testing under BS7671 and measurements taken to determine earthing requirements.

Class room

To finalise the electrical plans for this concrete designs are needed.

Current assumptions are:

Feed the lighting from the same supply that goes to the main toilet, via a conduit that's currently already partly through the entrance area. The actual lighting controls and feeds will depend on what sort of lighting to put in place.

Power sockets in the dado rails (we will need some way of keeping the sockets in the rails due to the use of. Do we also need some sort of hanging down sockets (we do have cable baskets still around)

Class room toilet

Assuming this is just going to require some sort of light with a pull switch to turn on. No emergency alarm is planned.

todo: has this now been removed from requirements

Weldy

One or two 32W LED panels the same as the back of the stage. The LED panels have been purchased, all that required is to fit them.

There are four standard 13A double sockets to be fitted. These are already purchased and require the time to fit them.

We have 16A and 32A C-form sockets available to fit if required.

Any other power for specific welders needs to be discussed. 3 phase can be fitted, but will require parts.

CNC

This requires proper lighting on our circuit and possibly more sockets.

The current landlord lighting and emergency lighting also goes through here. This needs to be tidied up. No further items should be required for this work.

Woody dusty

Sockets to be finished in here.

Emergency cutoff system to be fitted/specified

2 more LED light tube fittings are ready to be fitted.

Note, the "far" radial goes through here, we may require this to be moved so that the emergency cutoff can do all the sockets in there without removing power to that side of the space.

Other items

  • We will probably run out of 4mm2 cable. £105 for 100M
  • We may require more lighting cable. At worst £42 for 100M
  • General 20mm conduit and fittings.

Work for 2nd/3rd November

  • Get 3phase forom DB1 to DB2 to complete 3 phase work [postponed]
  • Finish lighting work in green room
    • Put the main light onto the switch [done]
    • Pull new cables for toilet and sink area [done]
    • Work out if any landlord lighting is still on there [done]
  • Get lighting (normal and EM) to the dark room [done]
    • Add switch and wiska box into dark room [done]
  • Put light up in toilet area
  • Move CNC lighting to new wiring [done]
  • Put new light up in CNC room
  • Put light(s) up in weldy area
  • Wire in new sockets added to end of dado circuit [done]
  • Add single socket into classroom for future work (and term current cable)
  • Finish sockets in weldy
  • Finish dado rail sockets
  • Map DB1 circuits
  • Map DB2 circuits
  • EM lighting check

To review:

  • Remove all old landlord lighting around permiter
  • Do we still have any other landlord lighting?
    • Cannot currently find anything
  • RCBOs needed for DBs
  • Any further work

Notes:

  • Adam was not available, so 3 phase work has been postponed

Work for 6th November

  • Tidy the lighting cabling in woody-dusty
  • Put light up in toilet area
  • Tidy wiring in toilet area
  • Finish disabled alarm and test
  • Start work on tidying wiring stuff in there

Work for 9th November

  • Put light(s) up in weldy area
  • Add single socket into classroom for future work (and term current cable)
  • Put light(s) up in weldy area
  • Finish EM work in lift area
  • Finish sockets in weldy
  • EM lighting check
  • Look at mounting water heater and wiring it in

Notes:

  • Weldy may require more clearing to get socket work done

EM light check:

  • most lights are working.
  • There is one not working above electronics (does not work at-all)
  • The two signs at the exits are not lasting 3hrs (about 2hrs)
  • The storage area one lasted 2+ hrs
  • The floodlight style in woody does not work at-all
  • The floodlight style above arts does not work at-all

Note, this check will need to be re-done when work is finished, there are still several EM lights that are not currently in service.

Work for 16th of Novermber

  • Bond earth to old incoming earth feed with 16mm
  • Add 3phase breaker to DB1
  • Install RCBOs into both DB1 and DB2
  • Fix grommet to meter on first floor
  • Add single socket into classroom for future work (and term current cable)
  • Finish EM work in lift area
  • Finish disabled alarm and test
  • Finish tidying wiring in toilet area

Notes:

  • classroom and toilet area work was not finished
  • DB1 is a memshield 2 board, 3 phase breaker will not fit
  • Arts EM light is dead, fuses checked and all seem ok, no power to light.

Work pre 30th/31st November

  • Finish EM work in lift area
  • Finish disabled alarm and test
  • Finish tidying wiring in toilet area
  • Add single socket into classroom for future work (and term current cable)
  • Fix emergency lighting above electronics

to work out:

  • Fixing emergency ligthing above the arts stage

possible fittings: https://www.cef.co.uk/catalogue/products/4759106-10w-led-non-maintained-emergency-twinspot-self-test-ip65 (£103)

https://www.cef.co.uk/catalogue/products/4305659-7w-led-maintained-emergency-bulkhead-ip65-white (£19.80)

possible boards (cef):

https://www.cef.co.uk/catalogue/products/1540713-4-way-tp-n-type-b-distribution-board-c-w-125a-switch-disconnector (£115.99)

https://www.cef.co.uk/catalogue/products/1540719-6-way-tp-n-type-b-distribution-board-c-w-125a-switch-disconnector (£128.96)

https://www.cef.co.uk/catalogue/products/1540729-100a-tp-switch-disconnector-incomer-kit (£46.99)

led tubes:

https://www.any-lamp.co.uk/noxion-avant-led-t8-tube-extreme-ho-em-150cm-20-6w-865-daylight-incl-led-starter-replaces-58w

Work for 30th/31st November

  • Either replace or get breaker fitted in DB1 for 3 phase
  • Fit RCBOs for DB1 and test
  • Remove switch/fuse unit on end of run above arts ramp
  • Add two emergency lights above the stage area

Only the switch/fuse work was done due to issues with transport.

We now have a pair of 40A 3 phase breakers and 5 C20A RCBOs for the DB1 replacement.

Members' meeting notes

  • initial build out wiring is comming to complete
    • only issues have been with dealing with exisiting infrat
    • new distribution power board now purchsaed
    • still need to fit RCBOs and run testing
  • we would note any future developments would be great if it required little extra work
    • a lot of work has already been put in to exisitng wiring work
  • woody dusty:
    • need to look into some sort of emergency stop system
    • agree to what needs to going into wiring
  • no "old" wiring to be touched

Work pre 14th/15th December

  • Extend trunking along from end of far radial to trunking into weldy
  • Pull back wiring already done in weldy for future building works
  • Finish EM work in lift area
  • Fix damaged EM black wire to EM light in metalworking
  • Tidy up toilet area
  • Initial review of revised layout work with Mark

Work for 14th/15th December

  • Remove old DB1, and replace it with the new board
  • Replace neutral cable on electricity meter
  • Connect 3 phase to DB2 properly
  • Possibly extend near and far radials to new board
  • Add conduit over from socket above arts to far trunking

Note. sockets in weldy have been removed by someone else.

Work early January 2020

  • Finish fixing the new trunking at top of arts ramp
  • Remove old EM light above arts, and route conduit for sockets move
  • Move arts dado supply to DB1
  • Prepare to move the lighting circuit conduit route for weldy and arts
  • Split near radial into woody-dusty
  • Move near, far radials to new board

Work 12th January 2020

  • Added conduit run and two sockets above main area

Work 20th/21st January 2020

  • Remove the wiring for old-snackspace fridges
  • Add wiring for the sockets above main
  • Look at metal strapping / options for SWA run for DB1 to DB2
  • Moved metalwork radial into new trunking
  • Tidied arts lighting and metalwork lighting cabling
  • Ordered metal straps and associated bits
  • Removed second soldering area light in preparation for walls

todo from this:

  • Re-fit missing trunking lids
  • Add metal conduit fixings for exit routes conduit
  • Look at whether metal strapping needed for cable trays

Work for 25th January 2020

  • Prep for putting all remaining trunking lids back
    • Add initial trunking exit for lights to classroom from toilet area
    • Tidy cabling up in tolet area
  • Finish the toilet emergency call wiring [not done]
  • Re-pull damaged cable to EM light in metal-working
  • Add socket new new snackspace and wire to RCBO in DB1 [not done]

Work for 27th January

  • Put trunking lids on as many areas as possible
  • Feed from toilet area to the EM light on the front door
  • Any extra SWA strapping possible
  • Finish emergency light addition in lift area

to get:

  • more M5x12 (one more pack of 25)
  • More red wallplugs

Work for 3rd Feb

  • Add EM light in lift area
  • Add initial conduit for new front door EM light circuit
  • Pul through some cables for light

Work for 4th Feb

  • Finish cables for new EM lighting on front door area
  • Add wiska box in the classroom area
  • Pull through cables for lighting power to the classroom area
  • Move the old 3core T&E to the new wiska box

Testing on 8th Feb

  • Testing done
  • Replaced MCBs in DB2 with RCBOs
  • Fixed light-switch orientation in main light switches
  • Swap out the unused switch for spare fish-switch
  • Fix EM to normal light power feeds

Work on 11th Feb

  • Initial conduit work for new light switch in snack area

Work on 15th Feb

  • Wired 2 switches and one key-switch in snack area
  • Put up tube from old electronics area with LED tube
  • Initial wiring for EM light above exit door

Notes:

  • EM lighting power not connected through yet
  • EM light is better centered above the door
    • but neither are actually centered in the alcove

Work on 13th May 2020

  • swapped EM light box for double box (for new EM light test)
  • added 3rd 10A RCBO to allow splitting of lighting circuits
  • tidied up wiska box in woody (mostly)

Look into getting fourth 10A RCBO and have woody on own lighting? Need to get another EM key switch to add to the box.

Work on 6th June 2020

  • Re-run the electrical testing for preparation for restart
  • Add two more EM light test switches
  • Check number of T8 light tubes to look at
  • Review EM stop for woody
  • Quick fire alarm test

Notes:

  • Fire alarm test not carried out, test keyswitch on panel broken

Work for 13th/14th June

  • Get new socket run done in woody dusty
  • Look at putting water heater up
  • Emergency light above slackspace entrance
  • Emergency light above inner entrance

Done:

  • Initial socket work, not finished

Work for 15th - 19th June

  • Get new socket run done in woody dusty
  • Look at putting water heater up
  • Emergency light above slackspace entrance
  • Emergency light above inner entrance

Work on 27th June

  • Finish and test new sockets in Woody Dusty
  • Fix power to the emergency light in green room
  • Review of issues with the historic wiring in slackspace

Work 30th June

  • Start fixing of sockets into Weldy
  • More work in conduit towards trunking in Woody

Work for 2 July

  • Finish trunking work in woody to finish socket radial
  • Finish fitting weldy sockets
  • More work to emergency light going into slackspace

possibly:

  • add a second EM light into storage area
  • look at EM light point in double emergency

Work 7th Nov 2020

  • Adam finished weldy sockets
  • Move flood light from snackspace to over arts (improve central EM light)

Work 14th Nov 2020

  • Initial sort of EM light above Metalwork door
  • Replacw 20W flood in lift area with 10W LED flood
    • Seems to be issue with LED array causing failure
    • Replaced with 10W as had stock, uncertain about area usage.

Work before restart

  • Possibly add second light in metalworking
  • Fix socket by DB1 and get it wired in.

Work 20th Nov 2020

  • Re-work the wiring near front-door/toilet for water heater
    • complete the conduit to water heater area
    • move the order of socket and connection for disabled toilet alarm
    • add new run from toilet-alarm connection to water heater.
  • start work on putting conduit from trunking into metalworking
    • Mark to finish this off when doing the plaster boarding
  • Untangle the wire coming out of DB2 into the trunking
    • This will allow trunking to be put back (wrapper with fire alarm FP200)
    • Pull wires back from "storage" area lights
    • Move wiska box for old electronics area one pillar back
    • Re-do the connections to the
  • Remove the main lighting in the green area
    • Also remove the light switch
    • Could permanently wire in the sink lights if needed
  • Remove two sockets on the green-area and arts wall
    • pulled cable back to cave area socket
  • Initial work on putting the EM light above weldy door
  • Discuss with Mark dissasembly of green room ceiling
    • Try and leave sockets in place
    • The lighting wiring into gree and cave is diffuclt to move
    • Try and keep the lighting wiring in place for now
      • Most of it is attached to edge of unit wall

Work 22nd Nov 2020

  • Remove cabling and light from the green area
  • Remove green walling (technically not electrical work...)
    • suspended old conduit above the green room
    • removed unused conduit from walls

thoughts:

  • photo-cave and old-green lighting could be re-routed, either:
    • extend on from metalwork and around in trunk
    • extend from snackspace area through and around
    • snackspace maybe shorter route.
    • this would also free up some of the arts wiska box (quite full)
    • temprarily we could just wire to plug and use a socket above green

Work 27th Nov 2020

  • Remove lighting feed to old green area
  • Moved stage wiska box to other side of stage
    • Closer to switch and stuff
    • Was very full with all connections elsewhere
    • Leaves spare wiska box for area over old green / etc
  • Only partially finished new box for stage

Work 29th Nov 2020

  • finish stage area rewire
  • run main area lights to wiska box prev running stage
  • reconnect the light and em light by the stage area
  • some work on metalworking em light conduit

Work 16th Jan 2021

  • put cover back on DB2 with one screw (tofix no more screws!)
  • put two cable tie bases in the trunk below DB2
    • note, we do have end caps for that trunk to fit
  • added Cform 32A connector to below DB2 and wired to 32A MCB
  • re-affixed fire cabling to top of trunking along pillars

Work 13th Feb 2021

  • added socket run for up to 4 desks for electronics area
    • left end with open 20mm conduit to continue round if needed
    • left spare 20mm point at start if needed (no 2 90deg bends)
    • in C20 RCBO in DB1
  • removed two sockets under DB2, freeing circuit
    • note, one socket with damaged outlet has been disposed of
  • added single double socket to wire ends in metalworking for now

Work 20th Feb 2021

  • Metalwork:
  • Move the tube batten from 1/2 to 1/3 way along beam
  • Add wiska box at 1/3 and 1/2 on the beam for lighting
  • More sorting of eletrical bits

Work for 23rd/24th Feb 2021

  • Measure up and spec last bits for metalworking
  • Look at trunking for emergeny light
  • Do some basic inventory for the electronics

Work for 6th March 2021

  • Add emergency light point above new woody fire-door
    • note, had to pull back socket cables to add conduit bits
  • Add new wiska box and second tube, em light in metal work
  • Add wiska box at back of metalwork for lighting (not wire yet)

Work for 13th March 2021

  • Get second run of conduit to back fire door
    • this is to be finished off once hoops founhd
    • then pull through the cables
  • Add most of conduit run along long wall in metalwork
  • Add second coduit down to main switch
  • Start work on internal-door wall in metalwork conduit for lighting

Work for 20th March 2021

  • Lighting conduit work in metalwork
  • Added second switch box for main switch
  • Moved woodworking to main switch panel
  • More work on metalwork lighting

Work for 30th March 2021

  • Conduit to cctv area for more sockets
  • Check items for easter weekend work
  • Re-add photocave lighting wiring

Work for 2nd-3rd April 2021

  • Fit run of 7 sockets along long wall in metal working
  • Start tidying work on trunking
    • issue with not enough cable retainers clips
  • Install toilet extraction fan and wire in
  • Add PIR into toilet to run lights and fan
    • Currently light switch can override both fan and light
  • Fitted keyswitch for entrace lighting
  • Put proper fire rated clips on entrance lighting

Work for 5th April 2021

  • Finish conduit for wiring to CCTV corner
  • Pull through the cable for CCTV corner socket(s)
  • Electronics area
    • Check all sockets and put the fronts on
    • Put all conduit covers on
  • Fit two sockets by DB1 for 3D printers
    • Added RCBO for these sockets
  • Re-fit screws on DB1 cover
  • Wire in sockets for metalworking
  • Start fitting covers on in toilet area

Notes:

  • need more covers for round trunking areas
  • need more 3.5x30 socket screws

Work 10th/11th April 2021

  • Put up two 10W LED lights in large storage
  • Add PIR for the new large storage lights
  • Remove sockets from wall between large storage and slackspace
  • Put one of above sockets back in where snackspace is currently
  • Finish lighting above lift area
    • Switch for turning on the emergrency light by lift
    • Put covering back on
  • Fix toilet seat
  • Measure bolts for putting DB2 cover back on
    • Think these are going to be M5x20mm
    • Seems to work
  • Returned size8 SWA cletes for size9
    • And scored some old cable drums for Mark
  • Lots of cleaning
  • Finish wiring toilet alarm
    • Unit is NC942B

Things to do before 12th April 2021 re-opening

  • Tidy cabling in member's storage
  • Finish metal-work lighting updates
  • Put covers back on DB2
  • Find correct screws for grid-switch fronts
  • Start fitting covers on conduit round things
  • Verify we have proper socket screws
  • Toilet alarm
  • Tidy wiring into lightswitch
  • Remove extra conduit from above main area

Notes from 27th June 2021

  • Light in snackspace seems to have failed (Noxion LED tube)
  • Tidy 4mm2 cables over entrance to cave
  • Put permanent live to the large storage PIR?
    • there is none on the wiska box above the front of stage
    • don't see any permanent live in feeder either
    • conclusion: leave this for now
  • tidy the PIR cabling and find a 20mm cable entry bushing

Work still to do

  • Add lighting point into member's storage area
    • re-use one of the LED floods from ?
    • need to re-add the EM light in there too
  • Add sockets into the snackspace area
  • Sockets in to the new snack/whatever area
  • EM stop for the woody and possibly metalworking area
  • Sockets for new electrical area (when design sorted)
  • Possibly new lighting in storage/electronics/etc area (when design final)
  • Lighting for the new snackspace/whatever area
  • EM light above the new fire door in woody
  • Put new light up in CNC room
  • Add 16/32A 3phase power into weldy
  • Possibly move all lights in metalworking onto central power
  • Fix EM flood in woody
  • Put covers on DB2
  • Finish metal clipping relevant conduit runs
  • Metal work sockets

Plus whatever happens once the various changes to layout have been discussed and finalised.

Other bits to do:

  • Fixup dado rail sockets
  • Changes in sockets once arts part-wall is odne
  • Map DB1 circuits
  • Map DB2 circuits
  • Second EM light test
  • Review the EM light once all areas are sorted
    • May need some extra lighting?

Possible outgoings for materials

weldy:

  • should currently have sufficient materials

cnc:

  • may need new light fitting for this
  • to cost - isolator/fuse for extraction fan

toilet:

  • should currently have materials to finish current work
  • may need extraction fan and appropriate isolator

green room:

  • should have all materials

slackspace:

  • light fittings t.b.d

full cost will require planning on exactly what is going where w.r.t to things like lighting.

the changes still need estimating and planning

emergency lighting:

  • to be determined once EM lights are tested

general:

  • 100M of 1.5mm2 single cables for lighting (4x£13.62) = £54.88
  • 100M of 4mm2 single cables for sockets (3x£35.40) = £106.20
  • May need some more 20mm conduit (£1.47 per 3M)
  • Misc conduit fittings (usually <£1 each)

Future spending

Some of these items will depend on the

  • Replacement of existing flourescent tubes with LEDs - to be discussed
  • Wiring of "classroom" - depends on what is needed

There may be more cable required, see cabling costs above. Possible £150

The RCBOs for the two DBs have been acquired off ebay, costs were: £60, £23.90, £22.90, £15.35, £26.96 = £152. This under half the original estimate for RCBOs that are better quality that originally specified.

November / December:

  • Replacement EM light for above arts, and an extra above ramp, approx £100
  • RCBO fitting to DB2, about £120 (already got most of this from ebay)

Installation standards

lighting is 1.5mm conduit singles, in the following colours:

  • green/yellow earth
  • brown is either live or swithced live
  • grey is switched live
  • black for emergency live
  • blue with black end tape emergency neutral

note, some of the old EM lighting is run on 1mm2 tripple, this uses:

  • brown for live
  • grey for neutral
  • black for emergency live

near is near the outside wall far is the one further from the outside wall

Metal fittings for phase 1 completion

The conduit for the lighting needs metal cable saddles fitting every 60cm for any bit which is above an area that people might move about.

Metal saddles are Screwfix code 5577J

(Conduit is the round white plastic tubing with wires in it)

Notes:

  • We do not need metal saddles on the runs down the sockets or light switches
  • The area in arts by the new electrical board has useful bits in it
    • 5x40 screws and the red plugs to go with them
    • Metal saddles (around 25 at current count, will go get more)
  • The red plugs and screws go with a 5-6mm dril
    • The plaster work isn't great, this can be drilled with a standard HSS...
  • We only have a couple of ladders capable of reaching the cross beams
  • The big yellow spirit level has a measure on the top

The large black SWA cabling currenly fixed onto the bottom of the trunking also is going to require extra fixing with metal ties. These will should be fitted between the existing black clamps (preferably middled).

Ties should be secured into the trunking using M5x12 bolts through the clamp bases. When drilling into trunking, place some wood between drill area and any wires to avoid issues with drilling into cable (this is bad).

Metal ties and bases are on order, and will be in for Saturday 25th. There is a pack of M5x12 bolts and M5 nuts on the area described above for the other supplies.

Meeting agenda, May 2020

  • any further splitting of the lighting
    • have now purhased 10A RCBO for DB
  • restart planning for post fire/covid
  • asbestos issues
  • woody sockets
  • woody emergency stop