This documents related to 2020-03, the Eclipse Foundation's multi-project Simultaneous Release of March 2020.
- Simultaneous Release Requirements (aka must-dos)
- Simultaneous Release Plan - Information that stays the same for each release, like requirements for participation, communication channels, etc.
Release |
Date |
Span |
Due dates |
Notes |
---|---|---|---|---|
2020-03 M1 |
Friday, January 17, 2020 |
01/10 to 01/17 |
|
3 weeks from 2019-12 GA |
2020-03 M2 |
Friday, February 7, 2020 |
01/31 to 02/07 |
3 weeks from M1 |
|
2020-03 M3 |
Friday, February 28, 2020 |
02/21 to 02/28 |
|
3 weeks from M2 |
2020-03 RC1 |
Friday, March 6, 2020 |
02/28 to 03/06 |
|
1 week from M3 |
2020-03 RC2 |
Friday, March 13, 2020 |
03/06 to 03/13 |
1 week from RC1 |
|
Quiet period |
03/13 to 03/17 |
No builds during "quiet period". It is assumed all code is done by the end of RC2. |
||
2020-03 GA |
Wednesday, March 18, 2020 |
|
5 days from RC2 |