p2psafety status 08.01.2014

oles-svider edited this page Jan 8, 2014 · 1 revision
  1. Open complexity: 12
  2. Average time per CP: 3:19
  3. This project time per CP: 8:46
  4. Maximum time per CP: 6:35
  5. Time required: 39:51 - 105:12 - 79:00
  6. Budget required: $1993.00 - $5260.00 - $3950.00
  7. Estimated completion date (1w moving average): Feb. 9, 2014 - March 27, 2014
  • March 9, 2014
  1. Time spent: 13:31
  2. Total time budget: 53:22 - 118:43 - 92:31
  3. Total budget: $2669.00 - $5936.00 - $4626.00
  4. Budget limit: $300.00