pritidesai
Copy link
Member

Changes

We can now specify a list of tasks needs to be executed just before
pipeline exits (either after finishing all non-final tasks successfully or after
a single failure)

Most useful for tasks such as report test results, cleanup cluster resources, etc

apiVersion: tekton.dev/v1beta1
kind: Pipeline
metadata:
  name: pipeline-with-final-tasks
spec:
  tasks:
    - name: pre-work
      taskRef:
        Name: some-pre-work
    - name: unit-test
      taskRef:
        Name: run-unit-test
      runAfter:
        - pre-work
    - name: integration-test
      taskRef:
        Name: run-integration-test
      runAfter:
        - unit-test
  finally:
    - name: cleanup-test
      taskRef:
        Name: cleanup-cluster
    - name: report-results
      taskRef:
        Name: report-test-results

Design doc: https://docs.google.com/document/d/1lxpYQHppiWOxsn4arqbwAFDo4T0-LCqpNa6p-TJdHrw/edit#

Part of #1684
Fixes #2446

Depends on: #2650

Submitter Checklist

These are the criteria that every PR should meet, please check them off as you
review them:

See the contribution guide for more details.

Double check this list of stuff that's easy to miss:

Reviewer Notes

If API changes are included, additive changes must be approved by at least two OWNERS and backwards incompatible changes must be approved by more than 50% of the OWNERS, and they must first be added in a backwards compatible way.

Release Notes

Users can now specify Tasks within a Pipeline that will always execute, even if Tasks fail, via the new `finally` clause

@tekton-robot tekton-robot added the do-not-merge/work-in-progress Indicates that a PR should not merge because it is a work in progress. label May 20, 2020
@tekton-robot
Copy link
Collaborator

[APPROVALNOTIFIER] This PR is NOT APPROVED

This pull-request has been approved by:
To complete the pull request process, please assign dibyom
You can assign the PR to them by writing /assign @dibyom in a comment when ready.

The full list of commands accepted by this bot can be found here.

Needs approval from an approver in each of these files:

Approvers can indicate their approval by writing /approve in a comment
Approvers can cancel approval by writing /approve cancel in a comment

@tekton-robot tekton-robot added the size/XXL Denotes a PR that changes 1000+ lines, ignoring generated files. label May 20, 2020
@tekton-robot
Copy link
Collaborator

This PR cannot be merged: expecting exactly one kind/ label

Available kind/ labels are:

kind/bug: Categorizes issue or PR as related to a bug.
kind/flake: Categorizes issue or PR as related to a flakey test
kind/cleanup: Categorizes issue or PR as related to cleaning up code, process, or technical debt.
kind/design: Categorizes issue or PR as related to design.
kind/documentation: Categorizes issue or PR as related to documentation.
kind/feature: Categorizes issue or PR as related to a new feature.
kind/misc: Categorizes issue or PR as a miscellaneuous one.

2 similar comments
@tekton-robot
Copy link
Collaborator

This PR cannot be merged: expecting exactly one kind/ label

Available kind/ labels are:

kind/bug: Categorizes issue or PR as related to a bug.
kind/flake: Categorizes issue or PR as related to a flakey test
kind/cleanup: Categorizes issue or PR as related to cleaning up code, process, or technical debt.
kind/design: Categorizes issue or PR as related to design.
kind/documentation: Categorizes issue or PR as related to documentation.
kind/feature: Categorizes issue or PR as related to a new feature.
kind/misc: Categorizes issue or PR as a miscellaneuous one.

@tekton-robot
Copy link
Collaborator

This PR cannot be merged: expecting exactly one kind/ label

Available kind/ labels are:

kind/bug: Categorizes issue or PR as related to a bug.
kind/flake: Categorizes issue or PR as related to a flakey test
kind/cleanup: Categorizes issue or PR as related to cleaning up code, process, or technical debt.
kind/design: Categorizes issue or PR as related to design.
kind/documentation: Categorizes issue or PR as related to documentation.
kind/feature: Categorizes issue or PR as related to a new feature.
kind/misc: Categorizes issue or PR as a miscellaneuous one.

@tekton-robot
Copy link
Collaborator

The following is the coverage report on the affected files.
Say /test pull-tekton-pipeline-go-coverage to re-run this coverage report

File Old Coverage New Coverage Delta
pkg/reconciler/pipelinerun/pipelinerun.go 73.5% 73.6% 0.1
pkg/reconciler/pipelinerun/resources/pipelinerunresolution.go 90.5% 93.1% 2.6

@pritidesai
Copy link
Member Author

/kind feature

@tekton-robot tekton-robot added the kind/feature Categorizes issue or PR as related to a new feature. label May 20, 2020
@tekton-robot
Copy link
Collaborator

The following is the coverage report on the affected files.
Say /test pull-tekton-pipeline-go-coverage to re-run this coverage report

File Old Coverage New Coverage Delta
pkg/reconciler/pipelinerun/pipelinerun.go 73.5% 73.6% 0.1
pkg/reconciler/pipelinerun/resources/pipelinerunresolution.go 90.5% 93.1% 2.6

@tekton-robot
Copy link
Collaborator

The following is the coverage report on the affected files.
Say /test pull-tekton-pipeline-go-coverage to re-run this coverage report

File Old Coverage New Coverage Delta
pkg/reconciler/pipelinerun/pipelinerun.go 73.5% 73.4% -0.1
pkg/reconciler/pipelinerun/resources/pipelinerunresolution.go 90.5% 92.6% 2.1

@tekton-robot
Copy link
Collaborator

The following is the coverage report on the affected files.
Say /test pull-tekton-pipeline-go-coverage to re-run this coverage report

File Old Coverage New Coverage Delta
pkg/reconciler/pipelinerun/pipelinerun.go 73.5% 73.3% -0.2
pkg/reconciler/pipelinerun/resources/pipelinerunresolution.go 90.5% 92.6% 2.1

@tekton-robot
Copy link
Collaborator

The following is the coverage report on the affected files.
Say /test pull-tekton-pipeline-go-coverage to re-run this coverage report

File Old Coverage New Coverage Delta
pkg/reconciler/pipelinerun/pipelinerun.go 73.5% 73.3% -0.2
pkg/reconciler/pipelinerun/resources/pipelinerunresolution.go 90.5% 92.6% 2.1

@tekton-robot
Copy link
Collaborator

The following is the coverage report on the affected files.
Say /test pull-tekton-pipeline-go-coverage to re-run this coverage report

File Old Coverage New Coverage Delta
pkg/reconciler/pipelinerun/pipelinerun.go 73.5% 73.3% -0.2
pkg/reconciler/pipelinerun/resources/pipelinerunresolution.go 90.5% 92.6% 2.1

@pritidesai pritidesai changed the title wip - implementing pipeline level finally WIP - implementing pipeline level finally May 20, 2020
@tekton-robot
Copy link
Collaborator

The following is the coverage report on the affected files.
Say /test pull-tekton-pipeline-go-coverage to re-run this coverage report

File Old Coverage New Coverage Delta
pkg/reconciler/pipelinerun/pipelinerun.go 73.5% 73.3% -0.2
pkg/reconciler/pipelinerun/resources/pipelinerunresolution.go 90.5% 92.6% 2.1

@tekton-robot
Copy link
Collaborator

The following is the coverage report on the affected files.
Say /test pull-tekton-pipeline-go-coverage to re-run this coverage report

File Old Coverage New Coverage Delta
pkg/reconciler/pipelinerun/pipelinerun.go 73.5% 73.3% -0.2
pkg/reconciler/pipelinerun/resources/pipelinerunresolution.go 90.5% 92.6% 2.1

@tekton-robot
Copy link
Collaborator

The following is the coverage report on the affected files.
Say /test pull-tekton-pipeline-go-coverage to re-run this coverage report

File Old Coverage New Coverage Delta
pkg/reconciler/pipelinerun/pipelinerun.go 73.5% 74.4% 0.9
pkg/reconciler/pipelinerun/resources/pipelinerunresolution.go 90.5% 92.6% 2.1

We can now specify a list of tasks needs to be executed just before
pipeline exits (either after finishing all non-final tasks successfully or after
a single failure)

Most useful for tasks such as report test results, cleanup cluster resources, etc

```
apiVersion: tekton.dev/v1beta1
kind: Pipeline
metadata:
  name: pipeline-with-final-tasks
spec:
  tasks:
    - name: pre-work
      taskRef:
        Name: some-pre-work
    - name: unit-test
      taskRef:
        Name: run-unit-test
      runAfter:
        - pre-work
    - name: integration-test
      taskRef:
        Name: run-integration-test
      runAfter:
        - unit-test
  finally:
    - name: cleanup-test
      taskRef:
        Name: cleanup-cluster
    - name: report-results
      taskRef:
        Name: report-test-results
```
@tekton-robot
Copy link
Collaborator

@pritidesai: The following tests failed, say /retest to rerun them all:

Test name Commit Details Rerun command
pull-tekton-pipeline-build-tests b26f852 link /test pull-tekton-pipeline-build-tests
pull-tekton-pipeline-unit-tests b26f852 link /test tekton-pipeline-unit-tests
pull-tekton-pipeline-integration-tests b26f852 link /test pull-tekton-pipeline-integration-tests
pull-tekton-pipeline-go-coverage b26f852 link /test pull-tekton-pipeline-go-coverage

Full PR test history. Your PR dashboard.

Instructions for interacting with me using PR comments are available here. If you have questions or suggestions related to my behavior, please file an issue against the kubernetes/test-infra repository. I understand the commands that are listed here.

@pritidesai
Copy link
Member Author

Messed up resolving conflicts, opened a new PR #2661 😭

@pritidesai pritidesai closed this May 21, 2020
Sign up for free to join this conversation on GitHub. Already have an account? Sign in to comment
Labels
do-not-merge/work-in-progress Indicates that a PR should not merge because it is a work in progress. kind/feature Categorizes issue or PR as related to a new feature. size/XXL Denotes a PR that changes 1000+ lines, ignoring generated files.
Projects
None yet
Development

Successfully merging this pull request may close these issues.

"Finally" tasks for Pipeline
2 participants