#Accessibilities
- Updated the example OMX files on the box account since walk transit (all modes) skims were required
- New accessibilities sub-model now working with an expression file
- Is included in the example, but doesn't overwrite the old accessibilities since all results will change
- Jeff posted in the Issue some questions for us to discuss
- Will merge branch into master by Friday
- Still need to update documentation
#Project admin
- Team agreed to defund task 5 and task 6 and create a new task 10 - Additional Revisions to Phase 1 Implementation
- AMPO has the revised contract scope language for review
- The goal of task 10 is to successfully run all phase 1 implemented sub-models for the full set of zones, skims, and households in order to eliminate any significant issues in the phase 1 components
- We will start on task 10 once we finish the accessibilities