-
Notifications
You must be signed in to change notification settings - Fork 100
Project Meeting 2020.10.15
Ben Stabler edited this page Oct 16, 2020
·
8 revisions
5b/6a Task 1 Project Management (milestone)
- Discussed getting started on the larch integration with new team member Jeff Newman, CS
- We added Jeff to this amendment to help with the Complete Estimation Mode task
5b Task 2 Strategic Planning (milestone)
- Comments on the updated version of the plan
- I added the optional test system paragraph, development roadmap, and tiered support
- Related to Maintaining support for multiple model implementations:
- Be more specific and provide examples for the exposing sections; what you would do in your region; add more proof
- Its not a user guide though, it is more high level, so we need to strike the right balance
- Move test system specifics afterwards since it supports the approach but isn't the approach
- Can partners take more ownership of this document?
- This will be a living document and having time to think things over and improve this over time has been helpful
- Both partners and consultants will contribute to it over time
- We should be more explicit about versioning this document
- @Alex and @Joe to discuss the current text, partner ownership, and setup time for partners to discuss
- @Bill to review
- No major revisions by me while it sits with Alex/Joe
- Related to Tiered Support:
- Three tiers - explicit support task for partners, smaller support only contract through AMPO, and just a time and materials type invoice
- What would be routed through AMPO? This may require a lot of work.
- Another idea is for third-parties to provide support like RedHat Linux for the Linux community
5b Task 10 Support for Three Zone Systems and TVPB (milestone)
- Marin example now running
- Starting on performance tuning / pre-computing / caching
- We need a better description of current memory usage for the example model to help understand these memory issues
- I'll put together a graphic of memory usage for the main process, the skims, for each multiprocess process, etc. for discussion
6a Task 3 Complete Estimation Mode (milestone)
- Starting on CDAP estimation larch notebook
- We're doing two major things in this task - adding estimation writers for trip models and adding more notebooks
6a Task 8 Maintenance and Support (milestone)
- Discussed tiered support ideas above