Project Meeting 2022.07.21
mnbina edited this page Jul 21, 2022
·
4 revisions
- Status Update on Phase 7 tasks
- Michelle to schedule an offline discussion about Phase 7 project delivery
- Jeff to schedule a side technical conversation about data types and making changes to the main (non-sharrow) version of ActivitySim to reduce run-time and memory usage.
- Task 2-4: Sharrow Parts 1-3
- Part 1 is almost done – should be done within a week or two
- Testing functionality is done
- Rigorous performance against old code – old code just takes a long time, with chunking turned as required by scope
- Concerns about not just run time but also memory usage – group wants Jeff to report on that during the next update. Jeff has been working on understanding both runtime and memory implications.
- This effort lead to discussions about reviewing data types that can be revisited.
- Joe proposes dealing with old data types, make a better version of the old version of the model, and then use this as the benchmark for comparison to sharrow, so that running the old version doesn’t become a barrier to completing work on time. Suggested that the consortium put together a task order for this and issue in the next two weeks.
- Jeff notes that it’ll be faster for him to get things done moving forward with what he’s already doing, rather than wait for a new task to be executed and then completed.
- Jeff TO DO: have a side technical conversation about this topic.
- Part 2 is getting 2- and 3-zone systems
- Moving along, more progress to share in 2-3 weeks
- Part 3 is time windows
- Smallest effort
- To be done in the next few months
- Task 5: Trying to find a time to present on the school drop-off and pick-up model
- Tours and trips are created
- Task 6: Disaggregate accessibilities
- Presenting next Tuesday
- Made synthetic population procedure for the disaggregate accessibilities
- Currently sending through the destination choice model
- Part 1 is almost done – should be done within a week or two
- Task 7: Shadow pricing – have not made much progress
- Task 8: Kind of incorporated into Task 5
- Michelle TO DO: Find a time offline to discuss timeline for project delivery
- Final deadlines
- Interim checkpoints