Project Meeting 2020.04.10
Ben Stabler edited this page Apr 13, 2020
·
10 revisions
Task 1 Project Management (milestone)
- Discussed draft Phase 6 scoping Google doc here
- Comments due 4/17
- First prioritization due 4/24
- Can tag issues with groups since many are similar
- Please add features if you want and write the description
Task 2 Strategic Planning (milestone)
- Discussed strategic development and contribution plan outline here
- Comments due 4/17
- We'll rename sections as Alex suggests
Task 4 I/O Improvements (milestone)
- No updates
Task 5 TNCs (milestone)
- Updated comparisons to latest TM1.5 match reasonably well given TM1 changes since asim fork
- TM1.5 was also re-calibrated and has some other improvements since asim fork
- Results confirm software improvements and so we'll finish adding TNCs to the tutorial now
Task 6 Model Developer Tutorial (milestone)
- Jupyter notebook recipe book coming along
- Make sure to double check all results before release
Task 9 Estimation Mode (milestone)
- Added writing of EDB to mandatory scheduling, which was tricky since work and school written at the same time
- About halfway through adding estimation mode to all submodels
- Team agrees to try and add functionality to all submodels
- Task budget may be an issue so we'll monitor it closely and potentially shift budget, likely from performance tuning, but that's for the PMC to decide
- Protect the multizone task budget too