Project Meeting 2020.07.17

Ben Stabler edited this page Jul 17, 2020 · 18 revisions

Task 1 Project Management (milestone)

  • Discuss Phase 6a scope
    • Alex is comfortable with the updates
    • Joe and I discussed adding Jeff Newman, the larch author, to the team to help with the estimation work and I discussed with Jeff and he's now added. I shifted hours from Binny the task cost increased a few thousand dollars.
    • Zephyr tutorial now planned for Monday, September 14th from 10:00 - 11:30 Pacific
  • Closed PR #323 to fix small min inbound departure times issue since the PR was to master and we're working on develop + it included some fixes already in the develop branch
  • Opened PR #325 from RSG develop to ActivitySim develop for recent work. Still working on website docs, but plan to finish soon and then pull for your review

Task 2 Strategic Planning (milestone)

  • Reviewed relevant information from peer projects like matsim, astropy, visioneval
  • Making some progress on the strategic development and contribution plan outline here

Task 3 Two Zones (milestone)

  • Need to work on documentation

Task 9 Estimation Mode (milestone)

Task 10 Support for Three Zone Systems and TVPB (milestone)

  • Making good progress on the three zone system revisions - do we have any technical questions from last time?
  • Discuss the need for a more complete example test data setup for exercising the functionality